The Department of Water and Sanitation (DWS) on Friday opened a second sluice gate at the Vaal Dam, as part of measures to manage increasing water levels and regulate substantial inflows into the dam.
This follows the opening of the first sluice gate on Thursday, 26 November, with the dam currently standing at 113.25% of its full supply capacity.
The department has urged communities living along the Vaal River to exercise extreme caution and keep away from overflowing rivers and flood-prone areas as controlled water releases continue.
The opening of the second sluice gate forms part of the department’s proactive dam management measures to regulate the increasing volume of water entering the Vaal Dam and safeguard the structural integrity of the dam. The decision follows continued monitoring of dam levels, inflows and prevailing hydrological conditions in the Integrated Vaal River System.
“Both sluice gates will remain open until further hydrological analysis and assessments determine the appropriate operational adjustments,” the department said in a statement.
As of this morning, the Vaal Dam was at 113.25% of its full supply capacity, with the water level recorded at 23.540 metres. Inflows into the dam stood at 652.35 cubic metres per second (m³/s), while the discharge was recorded at 151.910 m³/s. No rainfall (0 mm) was recorded, while evaporation stood at 6 millimetres.
The department said the high inflows into the Vaal Dam are largely attributed to recent rainfall in the upper catchment of the Vaal River System, which has generated increased runoff into the river network and subsequently into the dam.
The releases are also necessary to ensure the safe and coordinated operation of the broader Vaal River System, which comprises 14 dams operated as an integrated system.
“In particular, the controlled release of water from the Vaal Dam is intended to ensure that downstream Bloemhof Dam maintains its storage level at or below 90% of its full supply capacity. This requirement is particularly important because maintenance work is currently underway on the upstream side of the Bloemhof Dam wall.
“The dam’s storage level must therefore be maintained within the prescribed limit until the maintenance work has been completed. Managing inflows from the Vaal Dam is consequently critical to ensuring that Bloemhof Dam is not overwhelmed and that the ongoing maintenance work can proceed under the required operating conditions,” the department explained.
By gradually releasing water, the department said it aims to manage the volume and timing of downstream flows, particularly should further rainfall occur in the catchment.
This requires careful consideration of current inflows, anticipated runoff, water travel times, and the available storage capacity at downstream dams.
“Water released from the Vaal Dam will flow towards the Vaal Barrage and subsequently along the Vaal River towards Bloemhof Dam.”
Communities, farmers, and other water users situated along the Upper and Middle Vaal River, including Vereeniging, Vanderbijlpark, Vaalpark and Parys, are advised to anticipate possible changes in river levels and exercise extreme caution, particularly in low-lying areas and properties close to the river.
“Residents living in low-lying areas adjacent to the river are encouraged to remain vigilant and comply with any evacuation or safety instructions issued by relevant authorities. The public should also monitor official communication from the Department and disaster management structures for updates on dam operations and prevailing river conditions,” the department said. – SAnews.gov.za