Rand Water is scheduled to conduct major maintenance work on its key infrastructure starting Thursday, 29 May 2025. 

In a statement issued on Tuesday, Rand water said the maintenance is part of its commitment to ensuring a sustainable and efficient water supply.

“The objective of this planned maintenance is to increase capacity and enhance plant availability, reliability, and operational efficiency, supporting a more resilient and adaptable water supply network in preparation of the anticipated increased supply volumes from August 2025,” Rand Water said.

The entity said the maintenance activities will commence at different times and locations across various municipalities, with the main maintenance operation scheduled to start on Thursday at 3am, and anticipated to be concluded on Monday, 2 June, at 5pm.

Rand Water reported that during this period, pumping capacity will be reduced at the Eikenhof, Palmiet, Mapleton, and Zwartkopjes systems. 

Areas within the cities of Johannesburg, Ekurhuleni, and Tshwane may experience low pressure or intermittent water supply. 

“The maintenance may also impact water provision to the local municipalities of Rand West, Mogale City, Merafong, Madibeng, Lesedi, Govan Mbeki, Rustenburg, Royal Bafokeng Administration, and Victor Khanye, Thembisile Hani, Midvaal and Emfuleni. The maintenance work has been strategically scheduled during the low consumption months of May to July 2025, to minimise disruptions and better manage the potential impact on water supply,” the entity said.

The scope of work and associated impacts are outlined below:

City of Ekurhuleni Metropolitan Municipality

Description

Affected system

Planned date

Planned duration

   Impact on supply

Tie-in of B16 

pipeline from 

Zuikerbosch, 

Station 5

Mapleton System

From 29 May at 

03h00 to 02 June 

2025 at 17h00

107 hours

No pumping at Mapleton Pumping 

Station for the whole duration.

Klipriviersberg 

isolation for 

cleaning & inspection

Palmiet System

From 03 June 

2025 at 06h00 to 

16h00

10 hours

Pumping will be reduced to 67% 

for 10 hours.

Russel Road 

meter installation

Palmiet System

03 June 2025 

from 06h00 to 

18h00

12 hours

No supply to the following meters: 

Southern Areas, 

Barlow Road

Zwartkopjes 

Station valves 

replacements

Zwartkopjes 

System

From 30 June at 

05h00 to 02 July 

2025 at 07h00

50 hours

No pumping for the duration of the 

maintenance work.

 

The key objective for the major work is to connect the newly constructed B16 pipeline, which will be supplying water from the new Station 5A at Zuikerbosch Water Treatment Plant to Engine Room 3 at Mapleton Booster Pumping Station. 

The City of Ekurhuleni will also take an opportunity to carry out their maintenance in their electrical infrastructure.

City of Tshwane Metropolitan Municipality

Description

Affected system

Planned date

Planned duration

Impact on supply

Tie-in of B16 

pipeline from 

Zuikerbosch, 

Station 5

Mapleton System

From 29 May at 

03h00 to 02 June 

2025 at 17h00

107 hours

No pumping at Mapleton Pumping 

Station for the whole duration.

Klipriviersberg 

isolation for 

cleaning & 

inspection

Palmiet System

From 03 June 

2025 at 06h00 to 

16h00

10 hours

Pumping will be reduced to 67% 

for 10 hours.

The above-mentioned work will affect the City of Tshwane meters that are supplied from the above[1]mentioned systems.

City of Johannesburg Metropolitan Municipality

Description

Affected system

 Planned date

Planned duration

Impact on supply

Klipriviersberg 

isolation for 

cleaning & 

inspection

Palmiet 

System

03 June 2025 from 

06h00 to 16h00

10 hours

Pumping will be reduced to 67% 

for 10 hours.

Pipe leak 

repairs at 

Zuikerbosch 

Plan

Eikenhof 

System

 

48 hours

No pumping for 6 hours. It will be 

increased to 50% for 42 hours and 

then be increased 80% for the 

remaining 19 days.

Cleaning of 

Sedimentation 

Tank at 

Vereeniging 

Plant

Eikenhof 

System

30 June 2025 from 

05h00 to 21 July 

2025

21 hours

No pumping for 6 hours. It will be 

increased to 50% for 42 hours and 

then be increased 80% for the 

remaining 19 days.

Zwartkopjes 

Station valves 

replacements

Zwartkopjes 

System

30 June from 05h00 

to 02 July 2025 until 

07h00

50 hours

No pumping for the duration of the 

maintenance work.

The above-mentioned work will affect the City of Johannesburg meters that are supplied from the above1] mentioned systems.

Description

Affected system

Planned date 

Planned duration

Impact on supply

Pipe leak repairs at 

Zuikerbosch Plant

Eikenhof System

30 June 2025 

from 05h00 to 

02 July 2025 

at 05h00.

48 hours

No pumping for 6 hours. It 

will be increased to 50% for 

42 hours and then be 

increased 80% for the 

remaining 19 days.

Cleaning of 

Sedimentation 

Tank at 

Vereeniging Plant

Eikenhof System

 

30 June 2025 

from 05h00 to 

21 July 2025

 

21 days

No pumping for 6 hours. It 

will be increased to 50% for 

42 hours and then be 

increased 80% for the 

remaining 19 days.

The above-mentioned work will affect the Mogale, Merafong, Royal Bafokeng and Rand West meters that are supplied from the Eikenhof system.